Change order information
Announcement by Patricia - 4/7/2023 at 5:46 PM
Employee Post
Hi board - Andrew had passed along the following information related to the change order we had questions on Hammett Excavating. 

From what I understand the CO had to do with Hammett having to finalize the pond grading during their second mobilization of the final grading. This was due to the trailers being in the way when they first started the job. I don’t believe the initial plan was to export the dirt/rock as they were planning to use on other phases. However, due to the time in between the first and second mobilization, there was no place left to spread onsite and exporting was required. They did however reuse what rock they could around the pond in Phase 15. Unfortunately, the rest was needed to be exported. 
Board
Belmont FWSD